Project Timeline

Fall 2008:              Construction starts on UBC building and parkade at KGH

Fall 2008:              Construction starts on VJH Patient Care Tower

Winter 2009:        Construction starts on KGH Patient Care Tower

Nov 2009:             Cardiac revascularization services begin

Dec 2009:              UBC building and new parkade at KGH open

2011:                       VJH Patient Care Tower opens

2012:                       Open heart surgery begins

2012:                       KGH Patient Care Tower opens

2016/17:                 Interior Heart and Surgical Centre opens